Lab 18 • Agile Project Management & SRE
Project & Sprint Rescue Decision Lab
Rescue a delayed sprint on the critical path. Unblock downstream tasks, resolve developer overallocation (>7 days/sprint), and calculate updated project finish dates.
Dev 1 (Backend Lead)11 / 7 Days ⚠️ OVERALLOCATED
Dev 2 (Full-Stack)5 / 7 Days
Product Designer2 / 7 Days
Critical Path Dependency Graph
T1API Gateway Schema Migration
Assigned: dev1 • Duration: 3 days • Prereq: None
T2Payment Webhook Handler
Assigned: dev1 • Duration: 4 days • Prereq: t1
T3Checkout Mobile UI Layout
Assigned: designer • Duration: 2 days • Prereq: None
T4Stripe 3DS Error Handling Modal
Assigned: dev2 • Duration: 3 days • Prereq: t2
T5End-to-End Cypress Integration
Assigned: dev1 • Duration: 4 days • Prereq: t4
T6Production Canary Verification
Assigned: dev2 • Duration: 2 days • Prereq: t5